​​Well the ​weather has certainly been kinder to us over the past week and there has been lots of activity on-site, as the Contractors ​make great progress with the ground works for the new Pavilion.

The last section of the pile cropping has been completed with excavation now in progress for the drainage works.

Sports Redevelopment

The site continues to be extremely busy taking deliveries of materials for the build and another 10 tipper lorry-loads of soil has also been removed.  Two more now-redundant floodlights have also now been taken away.

Concrete, insulation, pipe bedding and filing stone will be delivered in the forthcoming week so that the installation of the drainage and duct work can continue along with installation of the ground beams.

Sports Redevelopment