It’s been pretty chilly for the contractors working on the new Sports Centre, but they’ve been forging ahead regardless. over the last week there’s been lots of progress, including:

  • Tanking protection to Ground Beams
  • Ground floor tanking
  • Fabricating
  • Concrete pouring
  • Steel Frame System to the parapet
  • Shuttering installed for concrete pour preparation
  • Installation of mesh
  • Lots of deliveries to site including steel mesh, membrane, mortar, Skip exchange wagons, scaffolding for the loading-bay, wall ties and fixings and two new scissor lifts

There’s plenty more planned for the next week too, but for the time being here’s a couple of photos to keep you going…