We hope that everyone had an enjoyable Easter break. There was no break from work however on the new Pavilion, with the size and the scale of the new building really starting to take shape.

The Contractors are installing the roof joists and forming the fascia and soffits for the roof. Roofing materials will soon be delivered to site and in the meantime the internal scaffolding in the building will be taken down and a second lift to the external scaffold will be added to allow installation of ply decking prior to the roofing contractor coming on-site.

Over at the rugby pitch essential stabilizing works have now been carried out and the new drainage will be installed hopefully this week. Labosport are due to inspect the work done and will report back to us in due course.